The upgrade of the Butwal-Gorusinge road into a climate-resilient four-lane highway has reached only 28 percent completion, with just one year remaining in the project timeline. The Rs13.55-billion infrastructure initiative is experiencing significant delays.
Progress on the highway is being hindered by multiple obstacles, including shortages of essential soil and riverbed materials. Additionally, delays in relocating utility poles and a sharp reduction in the available workforce have further slowed construction activities.