PURC engages Abofour-Dumasua residents over quality-of-service concerns amid faulty transformer

World 1 source 1 country 24m ago

The Public Utilities Regulatory Commission (PURC) says its intervention has led to the restoration of electricity supply to residents of Abofour-Dumasua in the Offinso South Municipality of the Ashanti Region. The community had been without power for several weeks after a faulty 200KVA transformer serving the area developed a fault in the first week of August. Residents subsequently lodged a complaint with the PURC’s Bono East Regional Office over the prolonged outage and delays in replacing the transformer.

Following the complaint, the Commission visited the community to engage residents and assure them of efforts to resolve the problem. It also engaged the Northern Electricity Distribution Company (NEDCo) and urged the utility provider to expedite the replacement of the faulty transformer. The delay had been attributed to a transportation challenge encountered by NEDCo, leaving residents without electricity for weeks.

On Wednesday, August 26, 2026, the PURC accompanied NEDCo to the community to supervise the replacement of the faulty transformer. Electricity supply was subsequently restored to the community. The Commission thanked residents for their patience and understanding during the period of the outage.

The residents, in turn, expressed appreciation to the PURC for its intervention and efforts to restore power to the community. The Public Utilities Regulatory Commission (PURC) has engaged residents of Abofour-Dumasua in the Offinso South Municipality of the Ashanti Region over a prolonged power outage caused by a faulty transformer. The residents lodged a complaint with the PURC’s Bono East Regional Office after a 200KVA transformer serving the community developed a fault in the first week of August, plunging the area into darkness.

The Northern Electricity Distribution Company (NEDCo), the service provider, has assured residents that it will replace the faulty transformer. However, the Techiman Area Office reportedly encountered transportation challenges, further delaying the repair works. The delay has left residents without electricity for about three weeks, worsening concerns within the community.

In response, the PURC on Monday, August 24, 2026, engaged community leaders and affected residents to address their concerns and assure them of efforts to restore power. The Commission directed NEDCo to expedite the replacement of the faulty transformer and restore electricity to the community by the end of the week. The engagement forms part of the PURC’s efforts to address consumer complaints and ensure utility providers meet their obligations to customers.